Start of the 2009 new dome project Mid-April
More photos of the start of the 2009 new dome project
Seats and Carpet removed from theater. May 2009
The dome is coming down. May 11th, 2009
Bare concrete is exposed. Insulation is gone. May 21st, 2009
New dome is delivered and starts going up. Second half of June 2009
The new dome frame is completed. June 18th, 2009
The first panels go on the dome. June 22nd, 2009
All the panels are on the dome. July 6th, 2009
The new carpet is installed. July 23rd, 2009
The seats are installed. July 28th through August 28th, 2009