ITC Fiber Assemblies


Project Start Date: Sat 8/1/98
Project Finish Date: Mon 10/30/00

Tasks

ID

Task Name

Duration

Start

Finish

% Complete

1

ITC Fiber Assemblies

576 days

Mon 8/3/98

Mon 10/30/00

0%

2

Design ITC fiber assemblies

6 wks

Mon 8/3/98

Fri 9/11/98

100%

3

Prototype ITC fiber assemblies

42 days

Thu 10/15/98

Fri 12/11/98

90%

4

Prepare components for Prototype

4 wks

Thu 10/15/98

Wed 11/11/98

100%

5

Develop assembly procedure

4 wks

Mon 10/19/98

Fri 11/13/98

100%

6

Make prototypes (1L+1R)

2 wks

Mon 11/16/98

Fri 11/27/98

100%

7

Ship prototype to UTA

1 wk

Mon 11/30/98

Fri 12/4/98

100%

8

Test prototypes

1 wk

Mon 12/7/98

Fri 12/11/98

50%

9

Protoypes finished

0 days

Fri 12/11/98

Fri 12/11/98

0%

10

Produce ITC fiber assemblies

481 days

Mon 12/14/98

Mon 10/30/00

5%

11

Iterate design and drawings

6 wks

Mon 12/14/98

Fri 1/22/99

100%

12

Find sources for components

6 wks

Mon 12/14/98

Fri 1/22/99

100%

13

Purchase components

10 wks

Mon 3/22/99

Fri 5/28/99

50%

14

Design assembly fixtures

2 wks

Mon 2/1/99

Fri 2/12/99

100%

15

Make assembly fixtures

4 wks

Mon 4/19/99

Fri 5/14/99

50%

16

Production (6R+6L/cycle)

352 days

Mon 5/31/99

Mon 10/16/00

0%

17

Production cycle 1

22 days

Mon 5/31/99

Wed 6/30/99

0%

18

Assemble tubing into guides

6 days

Mon 5/31/99

Mon 6/7/99

0%

19

Glue sleeves into plates

8 hrs

Mon 5/31/99

Mon 5/31/99

0%

20

Insert tubing into plate

16 hrs

Tue 6/1/99

Wed 6/2/99

0%

21

Pot tubing into plates

8 hrs

Thu 6/3/99

Thu 6/3/99

0%

22

Cure assembly

1 day

Fri 6/4/99

Fri 6/4/99

0%

23

Trim tubing

8 hrs

Mon 6/7/99

Mon 6/7/99

0%

24

Fiber gluing operations

7.25 days

Tue 6/8/99

Thu 6/17/99

0%

25

Mount plates, clips and plugs into rack

2 hrs

Tue 6/8/99

Tue 6/8/99

0%

26

Feed tubing through clips

8 hrs

Tue 6/8/99

Wed 6/9/99

0%

27

Cut fibers to length

4 hrs

Wed 6/9/99

Wed 6/9/99

0%

28

Insert fibers through tubes

16 hrs

Wed 6/9/99

Fri 6/11/99

0%

29

Glue fibers into plugs

4 hrs

Fri 6/11/99

Mon 6/14/99

0%

30

Cure epoxy

3 days

Mon 6/14/99

Thu 6/17/99

0%

31

Polish connectors

1.25 days

Thu 6/17/99

Fri 6/18/99

0%

32

Remove assemblies from rack

2 hrs

Thu 6/17/99

Thu 6/17/99

0%

33

Mount assemblies in polishing fixture

2 hrs

Thu 6/17/99

Thu 6/17/99

0%

34

Polish connectors

4 hrs

Thu 6/17/99

Fri 6/18/99

0%

35

Remove connectors

2 hrs

Fri 6/18/99

Fri 6/18/99

0%

36

Make connector light seals

3.5 days

Fri 6/18/99

Wed 6/23/99

0%

37

Inspect the connectors

4 hrs

Fri 6/18/99

Fri 6/18/99

0%

38

Attach clips

2 hrs

Mon 6/21/99

Mon 6/21/99

0%

39

Mount connectors in rack

2 hrs

Mon 6/21/99

Mon 6/21/99

0%

40

Insert sleeves into clips

2 hrs

Mon 6/21/99

Mon 6/21/99

0%

41

Pot sleeves into clips

8 hrs

Mon 6/21/99

Tue 6/22/99

0%

42

Cure RTV

1 day

Tue 6/22/99

Wed 6/23/99

0%

43

Remove connectors from the rack

2 hrs

Wed 6/23/99

Wed 6/23/99

0%

44

Test the assemblies

2 days

Thu 6/24/99

Mon 6/28/99

0%

45

Package/ship the assemblies

2 days

Tue 6/29/99

Wed 6/30/99

0%

46

Put assemblies into storage bags

4 hrs

Tue 6/29/99

Tue 6/29/99

0%

47

Make packaging

8 hrs

Tue 6/29/99

Wed 6/30/99

0%

48

Package assemblies

4 hrs

Wed 6/30/99

Wed 6/30/99

0%

49

Production cycle 2

3 wks

Thu 7/1/99

Thu 7/22/99

0%

50

Production cycle 3

3 wks

Fri 7/23/99

Thu 8/12/99

0%

51

Production cycle 4

3 wks

Fri 8/13/99

Thu 9/2/99

0%

52

Production cycle 5

3 wks

Fri 9/3/99

Fri 9/24/99

0%

53

Production cycle 6

3 wks

Mon 9/27/99

Fri 10/15/99

0%

54

Production cycle 7

3 wks

Mon 10/18/99

Fri 11/5/99

0%

55

Production cycle 8

3 wks

Mon 11/8/99

Tue 11/30/99

0%

56

Production cycle 9

3 wks

Wed 12/1/99

Tue 12/21/99

0%

57

Production cycle 10

3 wks

Wed 12/22/99

Mon 1/17/00

0%

58

Production cycle 11

3 wks

Tue 1/18/00

Mon 2/7/00

0%

59

Production cycle 12

3 wks

Tue 2/8/00

Mon 2/28/00

0%

60

Production cycle 13

3 wks

Tue 2/29/00

Mon 3/20/00

0%

61

Production cycle 14

3 wks

Tue 3/21/00

Mon 4/10/00

0%

62

Production cycle 15

3 wks

Tue 4/11/00

Mon 5/1/00

0%

63

Production cycle 16

3 wks

Tue 5/2/00

Mon 5/22/00

0%

64

Production cycle 17

3 wks

Tue 5/23/00

Mon 6/12/00

0%

65

Production cycle 18

3 wks

Tue 6/13/00

Mon 7/3/00

0%

66

Production cycle 19

3 wks

Tue 7/4/00

Mon 7/24/00

0%

67

Production cycle 20

3 wks

Tue 7/25/00

Mon 8/14/00

0%

68

Production cycle 21

3 wks

Tue 8/15/00

Mon 9/4/00

0%

69

Production cycle 22

3 wks

Tue 9/5/00

Mon 9/25/00

0%

70

Production cycle 23

3 wks

Tue 9/26/00

Mon 10/16/00

0%

71

Shipments to ANL

290 days

Fri 9/3/99

Mon 10/23/00

0%

72

Assemblies for ITC's 1-6

5 days

Fri 9/3/99

Fri 9/10/99

0%

73

Assemblies for ITC's 7-18

5 days

Tue 2/29/00

Mon 3/6/00

0%

74

Assemblies for ITC's 19-32

5 days

Tue 10/17/00

Mon 10/23/00

0%

75

Shipments to BCN

325 days

Fri 7/23/99

Mon 10/30/00

0%

76

Assemblies for ITC's 1-12

2 wks

Fri 7/23/99

Thu 8/5/99

0%

77

Assemblies for ITC's 13-36

2 wks

Tue 2/29/00

Mon 3/13/00

0%

78

Assemblies for ITC's 37-65

2 wks

Tue 10/17/00

Mon 10/30/00

0%

79

Start of Production

0 days

Mon 5/31/99

Mon 5/31/99

0%

80

First delivery to ANL

0 days

Fri 9/10/99

Fri 9/10/99

0%

81

First delivery to BCN

0 days

Mon 8/9/99

Mon 8/9/99

0%

82

Final delivery to ANL

0 days

Mon 10/23/00

Mon 10/23/00

0%

83

Fnal delivery to BCN

0 days

Mon 10/30/00

Mon 10/30/00

0%