Project Start Date: Sat 8/1/98
Project Finish Date: Mon 10/30/00
ID |
Task Name |
Duration |
Start |
Finish |
% Complete |
1 |
ITC Fiber Assemblies |
576 days |
Mon 8/3/98 |
Mon 10/30/00 |
0% |
2 |
Design ITC fiber assemblies |
6 wks |
Mon 8/3/98 |
Fri 9/11/98 |
100% |
3 |
Prototype ITC fiber assemblies |
42 days |
Thu 10/15/98 |
Fri 12/11/98 |
90% |
4 |
Prepare components for Prototype |
4 wks |
Thu 10/15/98 |
Wed 11/11/98 |
100% |
5 |
Develop assembly procedure |
4 wks |
Mon 10/19/98 |
Fri 11/13/98 |
100% |
6 |
Make prototypes (1L+1R) |
2 wks |
Mon 11/16/98 |
Fri 11/27/98 |
100% |
7 |
Ship prototype to UTA |
1 wk |
Mon 11/30/98 |
Fri 12/4/98 |
100% |
8 |
Test prototypes |
1 wk |
Mon 12/7/98 |
Fri 12/11/98 |
50% |
9 |
Protoypes finished |
0 days |
Fri 12/11/98 |
Fri 12/11/98 |
0% |
10 |
Produce ITC fiber assemblies |
481 days |
Mon 12/14/98 |
Mon 10/30/00 |
5% |
11 |
Iterate design and drawings |
6 wks |
Mon 12/14/98 |
Fri 1/22/99 |
100% |
12 |
Find sources for components |
6 wks |
Mon 12/14/98 |
Fri 1/22/99 |
100% |
13 |
Purchase components |
10 wks |
Mon 3/22/99 |
Fri 5/28/99 |
50% |
14 |
Design assembly fixtures |
2 wks |
Mon 2/1/99 |
Fri 2/12/99 |
100% |
15 |
Make assembly fixtures |
4 wks |
Mon 4/19/99 |
Fri 5/14/99 |
50% |
16 |
Production (6R+6L/cycle) |
352 days |
Mon 5/31/99 |
Mon 10/16/00 |
0% |
17 |
Production cycle 1 |
22 days |
Mon 5/31/99 |
Wed 6/30/99 |
0% |
18 |
Assemble tubing into guides |
6 days |
Mon 5/31/99 |
Mon 6/7/99 |
0% |
19 |
Glue sleeves into plates |
8 hrs |
Mon 5/31/99 |
Mon 5/31/99 |
0% |
20 |
Insert tubing into plate |
16 hrs |
Tue 6/1/99 |
Wed 6/2/99 |
0% |
21 |
Pot tubing into plates |
8 hrs |
Thu 6/3/99 |
Thu 6/3/99 |
0% |
22 |
Cure assembly |
1 day |
Fri 6/4/99 |
Fri 6/4/99 |
0% |
23 |
Trim tubing |
8 hrs |
Mon 6/7/99 |
Mon 6/7/99 |
0% |
24 |
Fiber gluing operations |
7.25 days |
Tue 6/8/99 |
Thu 6/17/99 |
0% |
25 |
Mount plates, clips and plugs into rack |
2 hrs |
Tue 6/8/99 |
Tue 6/8/99 |
0% |
26 |
Feed tubing through clips |
8 hrs |
Tue 6/8/99 |
Wed 6/9/99 |
0% |
27 |
Cut fibers to length |
4 hrs |
Wed 6/9/99 |
Wed 6/9/99 |
0% |
28 |
Insert fibers through tubes |
16 hrs |
Wed 6/9/99 |
Fri 6/11/99 |
0% |
29 |
Glue fibers into plugs |
4 hrs |
Fri 6/11/99 |
Mon 6/14/99 |
0% |
30 |
Cure epoxy |
3 days |
Mon 6/14/99 |
Thu 6/17/99 |
0% |
31 |
Polish connectors |
1.25 days |
Thu 6/17/99 |
Fri 6/18/99 |
0% |
32 |
Remove assemblies from rack |
2 hrs |
Thu 6/17/99 |
Thu 6/17/99 |
0% |
33 |
Mount assemblies in polishing fixture |
2 hrs |
Thu 6/17/99 |
Thu 6/17/99 |
0% |
34 |
Polish connectors |
4 hrs |
Thu 6/17/99 |
Fri 6/18/99 |
0% |
35 |
Remove connectors |
2 hrs |
Fri 6/18/99 |
Fri 6/18/99 |
0% |
36 |
Make connector light seals |
3.5 days |
Fri 6/18/99 |
Wed 6/23/99 |
0% |
37 |
Inspect the connectors |
4 hrs |
Fri 6/18/99 |
Fri 6/18/99 |
0% |
38 |
Attach clips |
2 hrs |
Mon 6/21/99 |
Mon 6/21/99 |
0% |
39 |
Mount connectors in rack |
2 hrs |
Mon 6/21/99 |
Mon 6/21/99 |
0% |
40 |
Insert sleeves into clips |
2 hrs |
Mon 6/21/99 |
Mon 6/21/99 |
0% |
41 |
Pot sleeves into clips |
8 hrs |
Mon 6/21/99 |
Tue 6/22/99 |
0% |
42 |
Cure RTV |
1 day |
Tue 6/22/99 |
Wed 6/23/99 |
0% |
43 |
Remove connectors from the rack |
2 hrs |
Wed 6/23/99 |
Wed 6/23/99 |
0% |
44 |
Test the assemblies |
2 days |
Thu 6/24/99 |
Mon 6/28/99 |
0% |
45 |
Package/ship the assemblies |
2 days |
Tue 6/29/99 |
Wed 6/30/99 |
0% |
46 |
Put assemblies into storage bags |
4 hrs |
Tue 6/29/99 |
Tue 6/29/99 |
0% |
47 |
Make packaging |
8 hrs |
Tue 6/29/99 |
Wed 6/30/99 |
0% |
48 |
Package assemblies |
4 hrs |
Wed 6/30/99 |
Wed 6/30/99 |
0% |
49 |
Production cycle 2 |
3 wks |
Thu 7/1/99 |
Thu 7/22/99 |
0% |
50 |
Production cycle 3 |
3 wks |
Fri 7/23/99 |
Thu 8/12/99 |
0% |
51 |
Production cycle 4 |
3 wks |
Fri 8/13/99 |
Thu 9/2/99 |
0% |
52 |
Production cycle 5 |
3 wks |
Fri 9/3/99 |
Fri 9/24/99 |
0% |
53 |
Production cycle 6 |
3 wks |
Mon 9/27/99 |
Fri 10/15/99 |
0% |
54 |
Production cycle 7 |
3 wks |
Mon 10/18/99 |
Fri 11/5/99 |
0% |
55 |
Production cycle 8 |
3 wks |
Mon 11/8/99 |
Tue 11/30/99 |
0% |
56 |
Production cycle 9 |
3 wks |
Wed 12/1/99 |
Tue 12/21/99 |
0% |
57 |
Production cycle 10 |
3 wks |
Wed 12/22/99 |
Mon 1/17/00 |
0% |
58 |
Production cycle 11 |
3 wks |
Tue 1/18/00 |
Mon 2/7/00 |
0% |
59 |
Production cycle 12 |
3 wks |
Tue 2/8/00 |
Mon 2/28/00 |
0% |
60 |
Production cycle 13 |
3 wks |
Tue 2/29/00 |
Mon 3/20/00 |
0% |
61 |
Production cycle 14 |
3 wks |
Tue 3/21/00 |
Mon 4/10/00 |
0% |
62 |
Production cycle 15 |
3 wks |
Tue 4/11/00 |
Mon 5/1/00 |
0% |
63 |
Production cycle 16 |
3 wks |
Tue 5/2/00 |
Mon 5/22/00 |
0% |
64 |
Production cycle 17 |
3 wks |
Tue 5/23/00 |
Mon 6/12/00 |
0% |
65 |
Production cycle 18 |
3 wks |
Tue 6/13/00 |
Mon 7/3/00 |
0% |
66 |
Production cycle 19 |
3 wks |
Tue 7/4/00 |
Mon 7/24/00 |
0% |
67 |
Production cycle 20 |
3 wks |
Tue 7/25/00 |
Mon 8/14/00 |
0% |
68 |
Production cycle 21 |
3 wks |
Tue 8/15/00 |
Mon 9/4/00 |
0% |
69 |
Production cycle 22 |
3 wks |
Tue 9/5/00 |
Mon 9/25/00 |
0% |
70 |
Production cycle 23 |
3 wks |
Tue 9/26/00 |
Mon 10/16/00 |
0% |
71 |
Shipments to ANL |
290 days |
Fri 9/3/99 |
Mon 10/23/00 |
0% |
72 |
Assemblies for ITC's 1-6 |
5 days |
Fri 9/3/99 |
Fri 9/10/99 |
0% |
73 |
Assemblies for ITC's 7-18 |
5 days |
Tue 2/29/00 |
Mon 3/6/00 |
0% |
74 |
Assemblies for ITC's 19-32 |
5 days |
Tue 10/17/00 |
Mon 10/23/00 |
0% |
75 |
Shipments to BCN |
325 days |
Fri 7/23/99 |
Mon 10/30/00 |
0% |
76 |
Assemblies for ITC's 1-12 |
2 wks |
Fri 7/23/99 |
Thu 8/5/99 |
0% |
77 |
Assemblies for ITC's 13-36 |
2 wks |
Tue 2/29/00 |
Mon 3/13/00 |
0% |
78 |
Assemblies for ITC's 37-65 |
2 wks |
Tue 10/17/00 |
Mon 10/30/00 |
0% |
79 |
Start of Production |
0 days |
Mon 5/31/99 |
Mon 5/31/99 |
0% |
80 |
First delivery to ANL |
0 days |
Fri 9/10/99 |
Fri 9/10/99 |
0% |
81 |
First delivery to BCN |
0 days |
Mon 8/9/99 |
Mon 8/9/99 |
0% |
82 |
Final delivery to ANL |
0 days |
Mon 10/23/00 |
Mon 10/23/00 |
0% |
83 |
Fnal delivery to BCN |
0 days |
Mon 10/30/00 |
Mon 10/30/00 |
0% |