Design ITC Fiber Assemblies
Aug. 3, 98
-
Oct. 30, 98
Done
-
Prototype Fiber Assemblies 
Oct. 15, 98
-
Nov. 27, 98
Done
-
Test prototype assemblies
Dec. 4. 98
-
Dec. 11, 98
Done
-
Iterate design 
Dec. 14, 98
-
Jan. 22, 99
Done
-
Purchase Components
Mar. 22,99
-
May, 28, 99
Done
-
Design Fixtures
Feb. 1, 99
-
Feb. 12, 99
Done
-
Make Fixtures
Apr. 19, 99
-
May 14, 99
Done
-
Production Cycle 1 

(6 pairs/ cycle)

May 31, 99
July 6, 99
June 30,99
Done 
Aug. 15,99
Production Cycle 2 
July 1, 99
Aug. 16, 99
July 22, 99
Done 
Aug. 30,99
Production Cycle 3
July 23, 99
Aug. 30, 99
Aug. 12, 99
Done 
Oct. 27, 99
Production Cycle 4
Aug. 13, 99
Sept. 13, 99 
Sep. 2, 99
Ready for Profiles
Nov. 26, 99
Production Cycle 5
Sep. 3, 99
Sept. 27, 99
Sep. 24, 99
Ready for Profiles
Nov. 26, 99
Production Cycle 6
Sep. 25, 99
Oct. 1, 99
Oct. 15, 99
Ready for Profiles
Nov. 26, 99
Production Cycle 7
Oct. 18, 99
   Oct. 6, 99
Nov. 5, 99
Ready for Profiles
Nov. 26, 99
Production Cycle 8
Nov. 8, 99
Oct. 11, 99
Nov. 30, 99
Ready for Profiles
Nov. 26, 99
Production Cycle 9
Dec. 1, 99
Oct. 14, 99
Dec. 21, 99
75
-
Production Cycle 10
Dec. 22, 99
Oct.  18, 99
Jan. 17, 00
75
-
Production Cycle 11
Jan 18, 99
Oct. 21, 99
Feb. 7, 00
25
-
Production Cycle 12
Feb. 8, 00
Oct.  25, 99
Feb. 28, 00
25
-
Production Cycle 13
Mar. 1, 00
Oct. 28, 99
Mar. 20, 00
25
-
Production Cycle 14
Mar. 21, 00
Nov. 1, 99
Apr. 10, 00
25
-
Production Cycle 15
Apr. 11, 00
Nov. 15, 99
May 1, 00
25
-
Production Cycle 16
May 2, 00
Nov. 29, 99
May 22, 00
25
-
Production Cycle 17
May 23, 00
Dec13, 99
Jun 12, 00
25
-
Production Cycle 18
Jun 13, 00
-
Jul 3, 00
-
-
Production Cycle 19
Jul 4, 00
-
Jul 24, 00
-
-
Production Cycle 20
Jul 25, 00
-
Aug. 14, 00
-
-
Production Cycle 21
Aug. 15, 00
-
Sep. 4, 00
-
-
Production Cycle 22
Sep. 5, 00
-
Sep. 25, 00
-
-
Production Cycle 23
Sep. 26, 00
-
Oct. 16, 00
-
-
Shipments to ANL
Sep. 10, 99
Oct. 21, 99
Oct. 23, 00
1 pair
-
Shipments to BCN
Aug. 23, 99
Oct. 4, 99
Oct. 30, 00
12  pairs
-