OpticsCycle


Project Start Date: Thu 8/26/99
Project Finish Date: Fri 1/14/00

Tasks

IDTask NameDurationStartFinishResource Names% Complete
1
MSU Cycle 1
49 daysFri 8/27/99Wed 11/3/99 0%
2
2 Mod'ls from ANL
1 dayFri 8/27/99Fri 8/27/99 0%
3
Optics Installation
38.25 daysWed 9/1/99Mon 10/25/99 0%
4
Instrument Mod'lA
18.38 daysWed 9/1/99Mon 9/27/99 0%
5
Prepare Mod'lA
10 hrsWed 9/1/99Thu 9/2/99 0%
6
Install tiles
11 hrsThu 9/2/99Fri 9/3/99 0%
7
Routing prep
3 hrsFri 9/3/99Fri 9/3/99 0%
8
Insert Profiles
29 hrsMon 9/6/99Thu 9/9/99 0%
9
Route Fibers
51 hrsThu 9/9/99Fri 9/17/99 0%
10
Glue Fibers
6 hrsMon 9/20/99Mon 9/20/99 0%
11
Secure Fiber Bundles
3 hrsWed 9/22/99Thu 9/23/99 0%
12
Polish Fibers
1 dayThu 9/23/99Fri 9/24/99 0%
13
Closeup the Module
7 hrsFri 9/24/99Fri 9/24/99 0%
14
Cleanup
3 hrsMon 9/27/99Mon 9/27/99 0%
15
Test Mod'lA
15 hrsMon 9/27/99Wed 9/29/99 0%
16
Instrument Mod'lB
18.38 daysMon 9/27/99Thu 10/21/99 0%
17
Prepare Mod'lB
10 hrsMon 9/27/99Tue 9/28/99 0%
18
Install tiles
11 hrsTue 9/28/99Wed 9/29/99 0%
19
Routing prep
3 hrsWed 9/29/99Wed 9/29/99 0%
20
Insert Profiles
29 hrsThu 9/30/99Tue 10/5/99 0%
21
Route Fibers
51 hrsTue 10/5/99Wed 10/13/99 0%
22
Glue Fibers
6 hrsThu 10/14/99Thu 10/14/99 0%
23
Secure Fiber Bundles
3 hrsMon 10/18/99Tue 10/19/99 0%
24
Polish Fibers
1 dayTue 10/19/99Wed 10/20/99 0%
25
Closeup the Module
7 hrsWed 10/20/99Wed 10/20/99 0%
26
Cleanup
3 hrsThu 10/21/99Thu 10/21/99 0%
27
Test Mod'lB
15 hrsThu 10/21/99Mon 10/25/99 0%
28
Pack Mod'lA
1 dayMon 11/1/99Mon 11/1/99 0%
29
Pack Mod'lB
1 dayTue 11/2/99Tue 11/2/99 0%
30
Ship 2 mod'ls to CERN
1 dayWed 11/3/99Wed 11/3/99 0%
31
MSU Cycle 2
56 daysFri 10/29/99Fri 1/14/00 0%
32
2 Mod'ls from ANL
1 dayFri 10/29/99Fri 10/29/99 0%
33
Optics Installation
55 daysMon 11/1/99Fri 1/14/00 0%

Resources

IDNameGroupMax UnitsPeak Units

Assignments

Task IDTask NameResource NameWorkStartFinish% Work Complete


This page maintained by: - RJM