Project Start Date: Thu 8/26/99
Project Finish Date: Fri 1/14/00
ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
---|---|---|---|---|---|---|
1 | MSU Cycle 1 | 49 days | Fri 8/27/99 | Wed 11/3/99 | 0% | |
2 | 2 Mod'ls from ANL | 1 day | Fri 8/27/99 | Fri 8/27/99 | 0% | |
3 | Optics Installation | 38.25 days | Wed 9/1/99 | Mon 10/25/99 | 0% | |
4 | Instrument Mod'lA | 18.38 days | Wed 9/1/99 | Mon 9/27/99 | 0% | |
5 | Prepare Mod'lA | 10 hrs | Wed 9/1/99 | Thu 9/2/99 | 0% | |
6 | Install tiles | 11 hrs | Thu 9/2/99 | Fri 9/3/99 | 0% | |
7 | Routing prep | 3 hrs | Fri 9/3/99 | Fri 9/3/99 | 0% | |
8 | Insert Profiles | 29 hrs | Mon 9/6/99 | Thu 9/9/99 | 0% | |
9 | Route Fibers | 51 hrs | Thu 9/9/99 | Fri 9/17/99 | 0% | |
10 | Glue Fibers | 6 hrs | Mon 9/20/99 | Mon 9/20/99 | 0% | |
11 | Secure Fiber Bundles | 3 hrs | Wed 9/22/99 | Thu 9/23/99 | 0% | |
12 | Polish Fibers | 1 day | Thu 9/23/99 | Fri 9/24/99 | 0% | |
13 | Closeup the Module | 7 hrs | Fri 9/24/99 | Fri 9/24/99 | 0% | |
14 | Cleanup | 3 hrs | Mon 9/27/99 | Mon 9/27/99 | 0% | |
15 | Test Mod'lA | 15 hrs | Mon 9/27/99 | Wed 9/29/99 | 0% | |
16 | Instrument Mod'lB | 18.38 days | Mon 9/27/99 | Thu 10/21/99 | 0% | |
17 | Prepare Mod'lB | 10 hrs | Mon 9/27/99 | Tue 9/28/99 | 0% | |
18 | Install tiles | 11 hrs | Tue 9/28/99 | Wed 9/29/99 | 0% | |
19 | Routing prep | 3 hrs | Wed 9/29/99 | Wed 9/29/99 | 0% | |
20 | Insert Profiles | 29 hrs | Thu 9/30/99 | Tue 10/5/99 | 0% | |
21 | Route Fibers | 51 hrs | Tue 10/5/99 | Wed 10/13/99 | 0% | |
22 | Glue Fibers | 6 hrs | Thu 10/14/99 | Thu 10/14/99 | 0% | |
23 | Secure Fiber Bundles | 3 hrs | Mon 10/18/99 | Tue 10/19/99 | 0% | |
24 | Polish Fibers | 1 day | Tue 10/19/99 | Wed 10/20/99 | 0% | |
25 | Closeup the Module | 7 hrs | Wed 10/20/99 | Wed 10/20/99 | 0% | |
26 | Cleanup | 3 hrs | Thu 10/21/99 | Thu 10/21/99 | 0% | |
27 | Test Mod'lB | 15 hrs | Thu 10/21/99 | Mon 10/25/99 | 0% | |
28 | Pack Mod'lA | 1 day | Mon 11/1/99 | Mon 11/1/99 | 0% | |
29 | Pack Mod'lB | 1 day | Tue 11/2/99 | Tue 11/2/99 | 0% | |
30 | Ship 2 mod'ls to CERN | 1 day | Wed 11/3/99 | Wed 11/3/99 | 0% | |
31 | MSU Cycle 2 | 56 days | Fri 10/29/99 | Fri 1/14/00 | 0% | |
32 | 2 Mod'ls from ANL | 1 day | Fri 10/29/99 | Fri 10/29/99 | 0% | |
33 | Optics Installation | 55 days | Mon 11/1/99 | Fri 1/14/00 | 0% |
ID | Name | Group | Max Units | Peak Units |
---|
Task ID | Task Name | Resource Name | Work | Start | Finish | % Work Complete |
---|