TileCalorimeter

Status of Optical Instrumentation at MSU

Person Responsible: RJM
Updated : June 14,2000
 Task
Link to
graphic
Target
Date
Status -
% Complete
Loading Dock Modifications
Drawing
Jun 15, 99
Complete
Module Transporter
Photos
Aug. 15, 99
Complete
  Design 
Drawings
May 31, 99
Complete
Module Stands
-
Aug. 15 ,99
Complete
Light Tent
-
Sept. 15, 99
Complete
Work Platforms
-
Sept. 1, 99
Complete
Mobile Tables
-
Sept. 15, 99
Complete
Materials Storage
-
Sept. 15, 99
Complete
Fiber separators
-
Sept. 30, 99
Complete
Fiber insertion tools
-
Sept. 30, 99
Complete
QC Systems
-
Sept. 15, 99
-
 Visual light source
-
June 30, 99
Complete
 Quantitiative light source
-
Sept. 30, 99
Complete
  Documentation &     procedures
-
Dec. 30, 99
75
 Stencils for labeling cells
-
Dec. 30, 99
Complete
 Fiber Routing Models
Photos
Oct. 16, 99
Complete
 Test Drawer
-
Oct. 15, 99
Complete
 DAQ Electronics
-
Oct. 15, 99
Complete
 DAQ/Analysis Computer
-
Aug. 15, 99
Complete
 Drawer Storage Box
-
  Feb. 25, 00
  Complete
Supplies & Equipment 
-
May 13, 02
-
 Glue mixing system
-
Jan. 17, 00
Complete
 Aspirin tubes
-
May 13, 02
2 modules
 Cable ties
-
May 13, 02
12 modules
 Dummy fibers
-
May 13, 02
On hand
Glue for fiber bundles
-
May 13, 02
Complete
 Labels with PMT cell numbers
-
May 13, 02
Print as needed
Laser fibers and connectors
-
May 13, 02
2 modules
Paint to draw cells
-
May 13, 02
On hand
Paper to cover modules
-
Oct. 15, 99
On hand
Profiles and WLS fibers
-
May 13, 02
2 modules
Rail to secure fibers
-
Sept. 15, 99
24 modules
Rail T's and mounting posts
-
May 13, 02
24 modules
Clips to hold fibers
-
May 13, 02
12 modules
Velcro Straps
-
Sept. 15, 99
On hand
Tape to secure profiles
-
May 13, 02
16 modules
ITC Fiber Assemblies
-
Oct. 30, 00
Production 75% completed
Polishing Machine
-
Sept. 15, 99
On hand
Packaging & Shipping 
-
Aug. 15, 99
-
Construct shipping bases
-
Aug. 15, 99
Done
Design shipping covers
-
July 30 , 99
Done
Construct shipping covers
-
Feb. 21, 00
As needed
Shipping contract
-
Feb. 21, 00
Complete