MODULE : ANL-023 @MSU |
ATLAS TILECAL OPTICS INSTRUMENTATION CHECK LIST |
|
REV: 2.5 Jan. 18, 2001 |
TASK |
DESCRIPTION |
Ref. Page |
1 |
MODULE PREPARATION |
|
2 |
TILES INSTALLATION |
|
3 |
ROUTING PREPARATION |
|
4 |
PROFILES AND FIBRES INSTALLATION |
|
5 |
FIBRES ROUTING |
|
6 |
FIBRES BUNDLES GLUING |
|
7 |
POLISHING AND CUTTING |
|
8 |
SECURE FIBRES BUNDLES |
|
9 |
||
10 |
||
NOTES |
|
Work crew should initial each task that they work on. Supervisor should indicate the date as each task is completed. QC person should fill in the report for each QC task. The QC tasks must be completed before subsequent tasks are started. Work crew shold fill in the materials list for all items used. Note any problems, deviations from procedures, suggestions, etc. in the space at the bottom and on the reverse side of pages. |
1. Module Preparation |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Task |
Description |
Date |
Work Crew |
|||||||||||||||||||||||||||||||||||||||||||||||||||||
1.1 |
Setup Module |
1-17-01 |
MN,RR, RJM |
|||||||||||||||||||||||||||||||||||||||||||||||||||||
1.2 |
QC0: |
1-18-01 |
RJM |
|||||||||||||||||||||||||||||||||||||||||||||||||||||
Item |
OK |
Not OK : List problems and repairs |
||||||||||||||||||||||||||||||||||||||||||||||||||||||
Residual Glue |
XX |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
Spring Pins |
X |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
Plate/Weld Bar Edges |
X |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
Submodule Shims and Spacing |
X |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
Pained Surfaces |
X |
Paint peeling from UC144 |
||||||||||||||||||||||||||||||||||||||||||||||||||||||
Slot Widths |
X |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
Contaminants |
X |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
Task |
Description |
Date |
Work Crew |
|||||||||||||||||||||||||||||||||||||||||||||||||||||
1.3 |
Clean out Slots |
1/22/01 |
MR |
|||||||||||||||||||||||||||||||||||||||||||||||||||||
1.4 |
Clean out Source Holes |
1/23/01 |
MR |
|||||||||||||||||||||||||||||||||||||||||||||||||||||
1.5 |
Cover Holes in Girder |
1/23/01 |
MR |
|||||||||||||||||||||||||||||||||||||||||||||||||||||
1.6 |
Drill & Tap Holes for belt and laser fiber connector |
2/04/01 |
DD |
|||||||||||||||||||||||||||||||||||||||||||||||||||||
1.7 |
Clean Module Surfaces |
1/24/01 |
PBL |
|||||||||||||||||||||||||||||||||||||||||||||||||||||
1.8 |
Mark Cell Boundaries |
1/26/01 |
MR, RW |
|||||||||||||||||||||||||||||||||||||||||||||||||||||
1.9 |
Install Cell & PMT Labels |
1/25/01 |
MR |
|||||||||||||||||||||||||||||||||||||||||||||||||||||
1.10 |
Ream Girder Rings |
1/25/01 |
MR |
NOTES:
2. Tile Installation |
|||||||||||||||||||||||||
Task |
Description |
Date |
Work Crew |
||||||||||||||||||||||
2.1 |
Measure gaps for shims |
1/26/01 |
MR |
||||||||||||||||||||||
2.2 |
Install Shims |
1/29/01 |
MR |
||||||||||||||||||||||
2.3 |
Record Tile Pak Numbers |
1/29/01 |
MR |
||||||||||||||||||||||
2.4 |
Insert Tiles |
1/29/01 |
MR, |
||||||||||||||||||||||
2.5 |
Insert Special ITC Tiles |
? |
? |
||||||||||||||||||||||
2.4 |
QC1: |
2/6/01 |
RJM |
||||||||||||||||||||||
Item |
OK |
Not OK : List problems and repairs |
|||||||||||||||||||||||
Tile Color |
X |
||||||||||||||||||||||||
Tile Sizes |
X |
||||||||||||||||||||||||
Tile End Surfaces |
X |
||||||||||||||||||||||||
Tile Wrappers |
X |
||||||||||||||||||||||||
Task |
Description |
Date |
Work Crew |
||||||||||||||||||||||
2.5 |
Install Rods |
X |
? |
NOTES:
3. Fiber Preparations |
|||||||||
Task |
Description |
Date |
Work Crew |
||||||
3.1 |
Install LED Light Tubes |
X |
RJM |
||||||
3.2 |
Label Bottom of Aspirin Tubes |
1/25/01 |
MR |
||||||
3.3 |
Install Aspirin Tubes and Washers |
1/25/01 |
MR |
||||||
3.4 |
Install Fixation Rails |
1/24/01 |
PBL |
||||||
3.5 |
Label Laser Fiber Bundles |
2/08/01 |
MR |
||||||
3.6 |
Install Laser Fiber Bundles |
2/08/01 |
MR |
||||||
3.7 |
Record Laser Fiber # |
2/9/01 |
MR |
||||||
3.8 |
Cover Girder Area |
2/09/01 |
MR |
||||||
3.9 |
Install ITC Fiber Supports |
? |
? |
NOTES:
4. Fiber/Profile Installation |
||||||||||
Task |
Description |
Date |
Work Crew |
|||||||
4.1 |
Setup Profile Shelves |
2/13/01 |
DD, DK |
|||||||
4.2 |
Record Profile Batch Numbers |
2/15 |
RW |
|||||||
4.3 |
Insert Profiles/WLS Fibers |
2/15 |
RW, AR, MR |
|||||||
4.4 |
Install Fiber Separator Wires |
? |
? |
|||||||
4.5 |
Install ITC Fibers |
2/16 |
RW |
|||||||
4.6 |
Record ITC Fiber # |
2/15 |
RW |
|||||||
4.7 |
Separate fibers by depth |
2-27 |
DK, AR |
|||||||
4.8 |
Make subbundles |
2/27 |
AR |
|||||||
4.9 |
QC2: Verify Sorting |
2/28 |
RJM |
|||||||
Item |
OK |
Not OK : List problems and repairs |
||||||||
Fiber Lengths |
X |
|||||||||
Fiber Counts |
X |
|||||||||
Depth Sorting |
X |
|||||||||
Visual Light Levels |
x |
2 fibers replaced |
||||||||
4.10 |
Remove Fiber SeparatorWires |
|
|
NOTES: 4.9 Sparkle defects on D fibers - RJM
5. Fiber Routing |
||||||||||||||||||||||||||||||||||
Task |
Description |
Date |
Work Crew |
|||||||||||||||||||||||||||||||
5.1 |
Route Sub-bundles To Aspirin Tubes |
3/14/01 |
RW, AR |
|||||||||||||||||||||||||||||||
5.2 |
Route the Laser Fibers |
3/20 |
RW |
|||||||||||||||||||||||||||||||
5.3 |
QC3: |
3/15 |
RJM |
|||||||||||||||||||||||||||||||
Item |
OK |
Not OK : List problems and repairs |
||||||||||||||||||||||||||||||||
Odd Side Cells |
|
See Notes |
||||||||||||||||||||||||||||||||
Even Side Cells |
|
See Notes |
||||||||||||||||||||||||||||||||
5.4 |
Insert Gluing tubes |
X |
||||||||||||||||||||||||||||||||
5.5 |
Insert Teflon Rods |
X |
||||||||||||||||||||||||||||||||
5.6 |
Register and Secure Fibers in Aspirin Tubes |
X |
||||||||||||||||||||||||||||||||
5.7 |
Insert Dummy fibers |
X |
||||||||||||||||||||||||||||||||
5.8 |
QC4: Check Fiber Damage |
3-21 |
RJM |
|||||||||||||||||||||||||||||||
Item |
OK |
Not OK : List problems and repairs |
||||||||||||||||||||||||||||||||
Broken fibers |
X |
|||||||||||||||||||||||||||||||||
Stress Crazing |
X |
See Notes |
||||||||||||||||||||||||||||||||
Cladding Damage |
X |
|||||||||||||||||||||||||||||||||
Fiber Curvature |
X |
|||||||||||||||||||||||||||||||||
Fiber Contact |
x |
|||||||||||||||||||||||||||||||||
5.9 |
Secure the Sub-bundles |
|
|
NOTES:
5.3 The laser fiber bundles should go to the outside of PMT's 1&2 - except for the fibers going to PMT's 1,2,3 - fixed by RJM
The L bundle to PMT10 is on the wrong side of R bundle to PMT12 (fixed, RJM)
The Laser fibers to PMT 42,44 were interchanged, fixed, RJM
Laser fiber to PMT7 should be on the outside of E1 bundle - fixed, RJM
Laser fiber to PMT13 is wrapped around the rail - too much stress - fixed, RJM
5.4 A15-PMT30 - The left bundle is misrouted to PMT34
B14- PMT34 - Right bundle is misrouted ot PMT30
B11 - PMT10 - Left bundle is entangled with the R bundle to A13-PMT12 - should go under it as per model
Laser fibers should be routed outside of PMT1 - see model
None of the bundles have been marked before inserting into the aspirin tubes
All Problems fixed by MN
.
6. Glue fiber bundles |
||||||||||||||||
Task |
Description |
Date |
Work Crew |
|||||||||||||
6.1 |
Prepare Glue Cartridges |
3-23 |
RJM |
|||||||||||||
6.2 |
Glue Odd Side |
3-23 |
MN. RR, RJM |
|||||||||||||
6.3 |
Glue Even Side |
3-23 |
MN. RR, RJM |
|||||||||||||
6.4 |
Reserve Samples of Epoxy |
X |
MN |
|||||||||||||
6.5 |
Epoxy Cure |
3-25 |
MN |
|||||||||||||
6.6 |
Remove Cable Ties from Silicon Tubes |
3-27 |
MN |
|
|||||||||||||||||
Task |
Description |
Date |
Work Crew |
||||||||||||||
7.1 |
Setup the Polishing Machine |
3-26 |
MN |
||||||||||||||
7.2 |
Polish Fibers, Odd Side |
3-26 |
MN |
||||||||||||||
7.3 |
Polish Fibers, Even Side |
3-26 |
MN |
||||||||||||||
7.4 |
Remove Polishing Machine |
3-26 |
MN |
||||||||||||||
7.5 |
QC5: Inspect Fiber Ends |
3-27 |
RJM |
||||||||||||||
Item |
OK |
Not OK : List problems and repairs |
|||||||||||||||
Surface Quality |
X |
||||||||||||||||
Visual Light Level |
X |
NOTES:
8. Secure fiber bundles |
||||||||||
Task |
Description |
Date |
Work Crew |
|||||||
8.1 |
Cut dummy fibers |
3-26 |
MN |
|||||||
8.2 |
Cut Gluing tubes |
3-26 |
MN |
|||||||
8.2 |
Tie FiberBundles to Rails |
3-26 |
MN |
|||||||
8.3 |
Install Cotton Belt |
3-27 |
RJM |
10. Close up |
|||||||||||
Task |
Description |
Date |
Work Crew |
||||||||
10.1 |
Cover Module with Plastic Sheet |
3-27 |
RJM |
||||||||
10.2 |
Cover Girder Ends |
4-12 |
RJM |
||||||||
10.3 |
Install Plastic Source Tubes |
4-12 |
RJM |
||||||||
10.4 |
Cover Source holes |
4-12 |
RJM |
||||||||
10.5 |
Tape ITC Fiber Support Panels |
3-26 |
RJM |
||||||||
10.6 |
Install Shipping Cover |
4-13,16 |
RW, MN |
NOTES:
|
|
Measured Widths (mm) |
Shims Required |
|||||||||||
Gap # |
Tile |
Oddside |
Even side |
1/2 |
3/4 |
1 |
||||||||
1 |
1 |
5.0 |
5.0 |
1 |
||||||||||
2 |
1 |
4.6 |
4.8 |
1 |
||||||||||
3 |
1 |
4.4 |
4.8 |
1 |
||||||||||
4 |
1 |
4.5 |
4.6 |
1 |
||||||||||
5 |
1 |
4.5 |
4.8 |
1 |
||||||||||
6 |
1 |
4.8 |
4.8 |
1 |
||||||||||
7 |
1 |
4.4 |
4.8 |
1 |
||||||||||
8 |
1 |
4.4 |
4.6 |
1 |
||||||||||
9 |
1 |
4.6 |
4.8 |
1 |
||||||||||
Total |
1 |
|
|
|
|
|||||||||
|
|
|
|
|
|
|
||||||||
1 |
11 |
4.8 |
5.1 |
1 |
||||||||||
2 |
11 |
4.4 |
4.4 |
|||||||||||
3 |
11 |
4.3 |
4.4 |
|||||||||||
4 |
11 |
4.5 |
4.4 |
|||||||||||
5 |
11 |
4.4 |
4.4 |
|||||||||||
6 |
11 |
4.4 |
4.6 |
1 |
||||||||||
7 |
11 |
4.5 |
4.4 |
|||||||||||
8 |
11 |
4.5 |
4.3 |
|||||||||||
9 |
11 |
4.5 |
4.6 |
1 |
||||||||||
Total |
11 |
NOTES: 1. Measure Tile Slot 1 at the bottom of the slot and Tile Slot 11 at the top
(where the widths are assumed to be minimum)
Tile Size |
Color |
Pkg.# (number of tiles) in order from ITC end |
|
|||||||||||||||||||||||||||||||||
1 |
Y |
1349,1352,1340,1354,1360,1351,1343 |
||||||||||||||||||||||||||||||||||
2 |
Y |
1341,1355,1327,1331,1410,1449,1390 |
||||||||||||||||||||||||||||||||||
3 |
Y |
399,458,392,226,382,454,455 |
||||||||||||||||||||||||||||||||||
4 |
Y |
87,164,346,92,227,345,223 |
||||||||||||||||||||||||||||||||||
5 |
Y |
120,411,149,320,365,195,470,311(2) |
||||||||||||||||||||||||||||||||||
6 |
Y |
295,256,250,156,251,280,286 |
||||||||||||||||||||||||||||||||||
7 |
B |
17,503,62,77,18,8,82,81 |
||||||||||||||||||||||||||||||||||
8 |
B |
31,476,114,507,423,154,432,13 |
||||||||||||||||||||||||||||||||||
9 |
B |
27,34,600,212,625,74,2,248 |
||||||||||||||||||||||||||||||||||
10 |
B |
142,451,474,197,471,469,218,210,449 |
||||||||||||||||||||||||||||||||||
11 |
B |
79,15,20,77,4,65,1,74,33 |
||||||||||||||||||||||||||||||||||
Date of BATCH |
||||||||||||||||||||||||||||||||||||
WLS/profile |
Long Profiles |
Short Profiles |
||||||||||||||||||||||||||||||||||
A12B11 |
1-23-01+ 2 from 11-2-00 |
|||||||||||||||||||||||||||||||||||
A13B11 |
1-23-01 |
1-23-01 |
||||||||||||||||||||||||||||||||||
A13B12 |
1-23-01 |
1-23-01 |
||||||||||||||||||||||||||||||||||
A14B12 |
1-23-01 |
1-23-01 |
||||||||||||||||||||||||||||||||||
A14B13 |
1-23-01 |
1-23-01 |
||||||||||||||||||||||||||||||||||
A15B13 |
1-23-01 |
1-23-01 |
||||||||||||||||||||||||||||||||||
A15B14 |
1-23-01 |
1-23-01 |
||||||||||||||||||||||||||||||||||
A16B14 |
1-23-01 |
1-23-01 |
||||||||||||||||||||||||||||||||||
A16B15 |
1-23-01 |
1-23-01 |
||||||||||||||||||||||||||||||||||
C10 |
||||||||||||||||||||||||||||||||||||
D4 |
||||||||||||||||||||||||||||||||||||
ITC Fibers #: |
Right: 73 |
Left: 73 |
||||||||||||||||||||||||||||||||||
Aspirin Tubes : |
||||||||||||||||||||||||||||||||||||
Laser Fiber #'s |
Odd Side: EB 91 |
Even Side:EB 94 |
||||||||||||||||||||||||||||||||||
Epoxy Batch # |
Resin:60C124428 EXP: 6/28/01 |
Hardner:70136110 |
Tile Layer |
Cell |
Side |
Tile * |
Problem |
Fixed ? |
QC2 |
|||||
10 |
D6 |
E |
2,35 |
Crazed fibers |
AR, 3-1-01 |
QC4 |
|||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
NOTE: Tiles are numbered from the beginning of the cell, starting at the tile closest to the ITC end of the module. Count every other profile to count the tiles. Odd tile layers start at the cell boundary (count from the first profile), even tile layers start with a spacer plate (count from the second profile). The tile counting stick makes it easier to locate the tiles.
This page maintained by: - RJM