With components supplied from: CERN, Chicago, Clermont-Ferand, Illinois, Lisbon, Pisa, Protvino, Texas Arlington, Yerevan
Goals:Assembly sites: Status of preparations:
- Optical instrumentation of 64 extended barrel modules
- Source testing of 64 extended barrel modules
ANL MSU
Schedule of operations: (mpp file, PS)Schedule of tasks in one period: (mpp file , PS)
- Starting in Aug 1999 and ending in Aug 2002
- 16 periods of 9 weeks at ANL
- 16 periods of 9 weeks at MSU
- In each period, 2 extended barrel modules will be instrumented and tested.
- The last period in each year is extended to 11 weeks.
Task Descriptions
- Each period consists of 8 weeks of scheduled tasks + 1 week for contingencies.
- Instrumentation of 2 modules can be done in parallel or in series.
- Source testing of a module can be done in parallel with instrumentation of other modules.
- Space is sufficient for next instrumentation cycle to begin before previous modules are shipped.
Materials: Quality Control procedures:
- ANL
- 0.5 FTE Mechanical Technician (supervisor, materials manager)
- 1.5 FTE Mechanical Technicians (scheduled tasks)
- 1 Physicist (QA, testing, documentation)
- MSU
- 0.5 FTE Mechanical Technician (supervisor, materials manager)
- 3.0 FTE Students (scheduled tasks)
- 1 Physicist (QA, testing, documentation)
Production monitor:
- QC Tasks
- Light Source Concept for visual checks (PostScript)
![]()