Quality Control tasks are indicated in red
Work Crew: t- senior technician; g- general technician or (2) students; QC- engineer or physicist
Task/sub tasks |
Work Crew |
Duration (hours) |
Manpower (manhrs) |
|
|
|
|
1) Prepare module: |
|
11 |
15 |
Secure module on assembly stand |
1t + 1g |
1 |
2 |
Setup work platforms, light tent, supplies tables |
2g |
1 |
2 |
QC0: Module Inspection |
QC |
1 |
1 |
Clean module surfaces |
1g |
2 |
2 |
Fix the rails that will hold the WLS/laser fibers |
1g |
2 |
2 |
Insert "aspirin" tubes |
1g |
2 |
2 |
Mark cell boundaries/numbers and label PMTs |
1t + 1g |
2 |
4 |
|
|
|
|
2) Install tiles: |
|
11-15 |
21-25 |
Insert tiles into slots |
1t + 1g |
8 |
16 |
QC1: Inspect tile installation |
QC |
1 |
1 |
Fix any displaced tiles or wrappers |
1g |
0-4 |
0-4 |
Install clamp rods |
1t + 1g |
1 |
2 |
Install temporary source tubes (for the EBs) |
1t + 1g |
1 |
2 |
|
|
|
|
3) Routing preparations: |
|
3 |
7 |
Install routing QC devices (light source) |
1t |
1 |
1 |
Install fiber separator wires |
1g |
1 |
1 |
Install ITC fiber assemblies (EB) |
1g |
1 |
1 |
Install the laser fiber bundles |
1t + 1g |
2 |
4 |
|
|
|
|
4) Insert profiles/fibers: |
|
29 |
58 |
Insert profiles into slots and sort fibers into depth segments |
2g |
22 |
44 |
QC2: Verify fiber lengths and sorting |
QC+ 1g |
4 |
8 |
Secure profiles with tape |
1t + 1g |
3 |
6 |
|
|
|
|
5) Route fibers: |
|
51-57 |
102-114 |
Make fiber sub-bundles |
1t + 1g |
6 |
12 |
Route sub- bundles to aspirin tubes |
2g |
18 |
36 |
QC3: Verify routing with a light source |
QC+1g |
6 |
12 |
Register and secure the fibers in the aspirin tubes |
2g |
12 |
24 |
QC4: Check registration and look for damaged fibers |
QC + 1t |
3 |
6 |
Repair damaged fibers |
1t + 1g |
0-6 |
0-12 |
Secure the sub-bundles along the girder |
2g |
6 |
12 |
|
|
|
|
6) Glue fiber bundles: |
|
6-54 |
12 |
Glue the fiber bundles into the tube |
1t + 1g |
6 |
12 |
Wait for the glue to cure |
|
48 |
0 |
|
|
|
|
7) Secure fiber bundles: |
|
3 |
5 |
Cut dummy fiber ends |
1g |
1 |
1 |
Tie fiber bundles inside the girder |
1t + 1g |
2 |
4 |
|
|
|
|
8) Polish the fiber ends: |
|
13 |
15 |
Setup the polishing machine in the girder |
1t + 1g |
2 |
4 |
Polish the fiber ends |
1t |
6 |
6 |
Remove the polishing machine |
1g |
2 |
2 |
QC5: Inspect the fiber ends |
QC |
2 |
2 |
Clean out the girder |
1g |
1 |
1 |
|
|
|
|
9) Insert and glue source tubes: |
NA |
Barrel |
Only |
Insert straight tube sections |
|
|
|
Insert and glue curved tube sections |
|
|
|
|
|
|
|
10) Close up the module: |
|
7 |
11 |
Remove the fiber separator wires and trays |
1g |
1 |
1 |
Remove temporary labels |
1g |
1 |
1 |
Cover the module with Aluminum sheet |
1t + 1g |
4 |
8 |
Attach girder end plates |
1g |
1 |
1 |
|
|
|
|
11) Cleanup |
|
3 |
5 |
Remove assembly fixtures and tables |
2g |
2 |
4 |
Remove empty boxes and tools |
1g |
1 |
1 |
|
|
|
|
12) Quantitative test and certification: |
|
15 |
20 |
Install drawers and cabeling |
QC+1g |
1 |
2 |
Install source system |
QC + 1g |
2 |
4 |
QC6: Quantitative test of module |
QC |
10 |
10 |
Remove drawers and cabeling |
QC+1g |
1 |
2 |
Remove source system |
QC + 1g |
1 |
2 |
|
|
|
|
13) Management |
|
0 |
45 |
Materials and supplies |
1t |
|
10 |
Scheduals and training |
1t |
|
20 |
Record keeping |
1t |
|
10 |
QC documentation |
QC |
|
5 |
|
|
|
|
Total (hrs.) |
t: 87-93 g:191-201 QC:38 |
152-210 |
316-332 |